Estimate erection: hours, crew and trucks

From a Scaffold plan: erection and dismantling hours, the crew, the days, the trucks and the weight per trip. No prices.

Your situation is different? Combine the modules: every document of a site in one conversation · How to create an accurate 3D scaffold plan with TektonAI

What you will get

The quantities to prepare your bid: erection and dismantling person-hours, crew, days, trucks and weight per trip, with no prices.

Before you start: create a TektonAI projectThe instructions to paste into Claude or ChatGPT, once and for all.

A project keeps instructions that apply to all its conversations. Create one for TektonAI: in every conversation, your assistant knows what our tools do and how you work, without you repeating it.

In Claude (tested)

  1. In Claude's left sidebar, open Projects, then Create project. Name it, for example “TektonAI”.
  2. In the project, open the project instructions and paste the text below. Replace the parts in brackets.
  3. Open a conversation in this project. In the conversation's tools menu, check that TektonAI is turned on.

On a Claude Team or Enterprise plan, share the project with your colleagues: they all start from the same instructions.

In ChatGPT (not tested)

  1. In ChatGPT's left sidebar, create a new project.
  2. In the project settings, paste the text below into its instructions.

TektonAI must first be added to ChatGPT: see Connect your AI assistant.

In Claude Code

Paste the text into the CLAUDE.md file of the folder you work in.

The instructions to paste

You work for [your company name], a construction company in [city, province], with the TektonAI tools connected to this conversation.

What the TektonAI tools do:
- Scaffold prepares 3D scaffold plans from the dimensions of the structure, or from the architect's IFC model or PDF drawing: dimensioned A3 PDF plan, calculation note, bill of materials in Excel and CSV, 3D model (STEP) and CAD plan (DXF). It revises an existing plan from its drawing number.
- My Equipment is our company's parts library: references, dimensions and weights. It imports our parts list.
- Scaffold plans use the parts of our library in My Equipment when we ask.
- Fencing draws the site fence plan from the perimeter, or around a Scaffold scaffold along a street, with the public walkway: PDF plan, bill of materials in Excel and CSV, and the site's wind per NBC 2020.
- Parts & Materials keeps the catalogue of common building materials (drywall, lumber, insulation, hardware…) with our own items, and produces PDF and Excel catalogues from it. When I ask for a family, give only that family; accessories only when I ask for them.
- Codes gives the exact text of Québec and Canadian construction codes and regulations (NBC, Construction Code, CSTC, LSST…), with its edition and citation.

How to work with me:
- Answer in English, in plain words and site terms. Produce documents (plans, calculation notes, catalogues) in English.
- Use the TektonAI tools for every plan, quantity or weight. Never make up a dimension, a quantity or a weight.
- Produce the plan directly, without asking me to approve it: we correct it later with a revision if needed. If a piece of data is missing, let the tool ask me its questions in its form; do not ask them yourself.
- When a tool asks me a question through a form, let me answer it myself. Never choose the duty class (light, intermediate or heavy) for me.
- Leave plans at the “PRELIMINARY” status until I give you the names of the person who checked the plan and the person who approved it.
- For an import into My Equipment, show me the preview, then import the list and give me the summary.
- Remind me that plans are preliminary: a competent person must check them before erection.

The same text is also at tektonai.app/en/project-instructions.md.

To prepare a bid, you need quantities: how many hours, how many people, how many trucks. Scaffold works them out from the plan’s bill of materials. It gives no prices: you apply your own rates.

Julie Exemple, of Entreprise Démo TektonAI, is preparing the bid for the 3-storey sixplex in Montréal. Her plan is ECH-261029-E16A: the street façade, 453 parts.

What you need

  • A Scaffold plan. See Create a 3D scaffold plan.
  • Your own rates, if you have them: the crew size, the hours per day and your truck’s load. Without them, Scaffold uses its reference rates and says so.

Step 1: ask for the estimate

Estimate the erection of scaffold ECH-261029-E16A: the hours, the crew and the trucks.

Scaffold answers:

Erection estimate · plan ECH-261029-E16A rev. A · Sixplex de 3 étages, façade sur rue

Result Value
Erection 19.1 person-hours
Dismantling 11.4 person-hours
Crews and people 1 × 4 = 4
Erection / dismantling days 1 / 1
Time on site 2 days
Trucks (delivery trips) 2
Weight counted / heaviest trip 3662 kg / 3000 kg

Julie reads:

  • 19.1 person-hours to erect and 11.4 to dismantle;
  • a crew of 4 people: 1 day to erect, then 1 day to dismantle;
  • 2 days on site;
  • 2 truck trips, the heaviest carrying 3,000 kg (6,614 lb).

The answer also breaks the hours and weights down by part category: bases, structure, bracing, platforms, access, guardrails and toeboards, and ties.

It worked when: The estimate gives the erection and dismantling person-hours, and the number of trucks.

Step 2: read the assumptions

Before you put the figures in your bid, read the assumptions:

Assumptions:

  • Durations calculated with the tool’s reference rates (crew of 4 people, 8.0 h per day, dismantling at 0.60 times the erection, 3000 kg truck, a single crew); a faster or slower crew changes these durations in proportion.
  • Reference rate: person-minutes of fitting per part according to its category, plus 0.04 minute per kg of part when its weight is known.
  • The return at dismantling follows the same truck trips.
  • Quantities and weights: bill of materials of plan ECH-261029-E16A, revision A.
  • Days are rounded up to whole days; the time on site adds erection and dismantling.

Julie did not give her rates: the estimate uses the tool’s. If your crew has 3 people, or your truck carries more, say so in the request.

Then read the points to note:

Points to note:

  • Volume per trip not counted: the packing dimensions of the parts are not provided.
  • Lifting equipment capacity not provided: suitability not assessed (heaviest part: Hatch deck 10’, 33.2 kg).

It worked when: You know which rates the estimate used, and what it does not count.

Step 3: the estimate files

Scaffold delivers the estimate as a PDF, on 1 A3 sheet, and as Excel. The PDF shows the results, the breakdown by part category and the truck trips:

Trip Parts Weight (kg)
1 254 2999.8
2 199 662.6

Erection estimate for plan ECH-261029-E16A: results, breakdown by part category, truck trips, points to note and assumptions. The reference and the QR code are blurred

Like the plans, the estimate carries a TektonAI reference you can check. See Check that a TektonAI plan is authentic.

It worked when: You have the estimate's PDF and Excel file.

Good to know

  • No tool gives prices.
  • The quantities and weights come from the plan’s bill of materials. The weights are indicative.
  • A revision of the plan changes the bill of materials: ask for a new estimate for the new revision.

What's next

Combine the modules: every document of a site in one conversationFrom the scaffold plan to the list of laws and standards: each tool picks up the previous one's work and delivers its own document, with its reference.Read the tutorial ›
No TektonAI account yet?Accounts open by invitation, after a price request.

Request a price

Make your list. We will reply with a price for your company.

1 What I want
2 What I am looking for

A job you would like to hand to an AI tool. One line per need.

    3 Who I am

    We use this information only to answer you and prepare your price. We record it in a customer profile at Stripe, our billing provider, and email it to our team. See our privacy policy.

    Tap the plan to zoom in or out.Click the plan to zoom in or out.